Port Update: Public comment period Oct 15 to Nov 14 regarding Centerm Expansion Project permit extension to April 30, 2023

There’s a 30-day public input comment period regarding the sought extension of the permit for the Centerm Expansion by a year. Further information about the permit amendment review can be found in the text of the letter reproduced below (emphasis added):

The Centerm Expansion Project and South Shore Access Project received a project permit from the port authority in April 2018, and the current permit will expire on April 30, 2022. The port authority is seeking an amendment to extend the project permit up to April 30, 2023.

While the construction of all components are progressing well in the midst of a global Covid-19 pandemic, the project completion date is now expected to be in April 2023. This permit amendment will allow the project flexibility to complete some construction activities before the project can be deemed complete.

The Centerm Expansion Project and South Shore Access Project is the largest infrastructure project that the Vancouver Fraser Port Authority has ever undertaken. The project includes an expansion of Centerm Container Terminal, and updates to port roads along the south shore, which connect to and service the terminal.

As part of the port authority’s permit amendment review process, a notice has been posted on the Impact Assessment Agency website and a 30-day public comment period is being held from October 15, 2021 to November 14, 2021. The public will have an opportunity to provide feedback on the permit amendment request by visiting this website.

We greatly appreciate your patience and understanding as we complete this important project as safely and efficiently as possible.

If you have questions about this project, please feel free to contact the project team at centerm.expansion@portvancouver.com or by phone at 604.665.9563. For more information about these projects, visit www.portvancouver.com/centerm-expansion.